The worlds oldest nuclear waste store has been cut open for the first time.

Experts at the Sellafield nuclear site have cut the hole in the Pile Fuel Cladding Silo, a locked vault which was never designed to be opened.

This is the first of six holes that will allow radioactive waste to be removed from one of the sites most hazardous buildings.

The silo was built in the 1950s when the sites purpose was to make material for nuclear weapons.

Safely decommissioning the building is one of the highest priorities for Sellafield Ltd and the Nuclear Decommissioning Authority, and will take them a step closer to reducing the UKs nuclear hazard.

The most complicated hole in a wall ever made

Steven Carroll, Head of the Pile Fuel Cladding Silo, said:

I am incredibly proud of the work that our Sellafield Ltd and supply chain teams have achieved together, in preparing the silo for successful waste retrievals.

The level of challenge involved with this facility is unparalleled, considering the age of the building, the lack of historical information about the waste itself, the atmosphere inside the silo and its positionon one of the most congested sites, anywhere in the world.

Despite this, the teams have carried out some world class engineering in difficult environments to get us closer to getting the waste out and into safer storage earlier than planned.

The work is being carried out by Sellafield Ltd, along with Bechtel Cavendish Nuclear Solutions and Babcock Marine Technology.

Preparations have been under way for a number of years, which involved practising the cutting operation at a full-scale replica test rig in Rosyth, Scotland.

The six holes are cut at the top of each of the facilitys six compartments, allowing access to the waste within the silos walls for the first time in 65 years.

Each section is cut away in a single piece and withdrawn into a containment bag. A containment door is then lowered over the aperture and closed.

The giant steel doors will provide a safe barrier between the waste inside the silo and the outside world. Work to remove the material will start in 2019.

To remove the waste, a crane will extend through the cut holes, a grabber will then drop down to scoop the waste up, lifting it out of the container and back through the hole.

It will then be dropped into a specially-designed metal box, for safe and secure storage in a modern facility.

Related Articles

Comments

  1. We don't have any comments for this article yet. Why not join in and start a discussion.

Write a Comment

Your name:
Your email:
Comments:

Post my comment

Recent Comments

Follow Us on Twitter

Share This


Enjoyed this? Why not share it with others if you've found it useful by using one of the tools below: