Fees are payable for different types of project based on the time it takes the Marine Management Organisation (MMO) and the Centre for Environment, Fisheries and Aquaculture Science to process the application.

An MMO case manager will notify you of the suitable fee band for your application. This can be changed if new information about your project makes a different band more suitable. If your application is moved to a different band, MMO will seek your agreement before doing any further work.

Where an application is to carry out more than 1 licensable activity and they fall in different fee bands, the higher fee band is payable.

For example, an application to dredge material and dispose of it at sea includes a band 3 project (dredging) and a band 2 project (disposal if fewer than 1 million cubic metres), so the fees applied to the application will be band 3.

From 1 April 2019, the MMO will recover the costs for carrying out marine licence monitoring inspections for all existing licences that expire after 1st April 2020 and all new applications received after 1st April 2019.

Further information

See how to get a licence for a burial at sea.

Contact information

Contact the Marine licensing team

Published 11 June 2014
Last updated 31 March 2024 +show all updates

Related Articles

Comments

  1. We don't have any comments for this article yet. Why not join in and start a discussion.

Write a Comment

Your name:
Your email:
Comments:

Post my comment

Recent Comments

Follow Us on Twitter

Share This


Enjoyed this? Why not share it with others if you've found it useful by using one of the tools below: