GovWire

Guidance: Section 62A Planning Application: S62A/2024/0051 Land West of Thaxted Road Saffron Walden

Planning Inspectorate

August 30
14:54 2024

Type of application:

Application for Approval of Reserved Matters following Outline Approval

Applicant name

Chase New Homes

Site address:

Land West of Thaxted Road Saffron Walden

Description of proposed development

Erection of 168 dwellings with associated landscaping and parking

Case Officer

Section 62A Applications Team

Procedure

TBC

Key dates

Date
Date application valid 25 July 2024
Date by when representations must be made 30 August 2024
Hearing date and venue TBC
Target decision 24 October 2024
Decision date TBC

Hearing Documents

Decision

Make a representation

The application can be inspected under the application plans and documents heading below.

You will be able to comment on this application until 30 August 2024

Please base your comments on planning matters.

Please avoid the use of inflammatory, discriminatory or abusive comments

All representations made in connection with the development proposal will be made publicly available on the website shortly after the end of the representation period. The name of the individual author or organisation will be published however addresses, signatures and contact details will not be published. We advise you not to include any other personal information about yourself or others.

OurCustomerPrivacy Noticesets out how we handle personal data in accordance with the law.

Send your comments via email to section62a@planninginspectorate.gov.uk

or write to

Section 62A Applications Team,
The Planning Inspectorate,
3rd Floor, Temple Quay House,
2 The Square, Temple Quay,
Bristol,
BS1 6PN

Sending comments by email will enable us to deal with them more quickly and is preferred.

Please include the application reference number S62A/2024/0051 and site address.

This application will be determined by an Inspector appointed by the Secretary of State. Shortly after the close of the representation period the Planning Inspectorate will consider whether a hearing is necessary. In the event that a hearing is scheduled, and you would wish to speak at the hearing, you must make this request at the time you submit your written representations.

Where the application is to be considered at a hearing, notice of the date, time and venue for the hearing along with the name of the person holding the hearing, will be published on this website at least two weeks before the date of the hearing.

Application Plans and Documents

Related Articles

Comments

  1. We don't have any comments for this article yet. Why not join in and start a discussion.

Write a Comment

Your name:
Your email:
Comments:

Post my comment

Recent Comments

Follow Us on Twitter

Share This


Enjoyed this? Why not share it with others if you've found it useful by using one of the tools below: