Planning Inspectorate
Type of application:
Full Planning Application
Applicant name
Pelham Structures Ltd
Site address:
Land adjacent to Village Hall, East of Cambridge Road, Ugley, Bishops Stortford, Hertfordshire, CM22 6HR
Description of proposed development
Construction of 16 dwellings including 40% affordable housing and associated infrastructure at Land East of Ugley Village Hall.
Case Officer
Section 62A Applications Team
Procedure
TBC
Key dates
Date | |
---|---|
Date application valid | 27 August 2024 |
Date by when representations must be made | 3 October 2024 |
Hearing date and venue | TBC |
Target decision | 26 November 2024 |
Decision date | TBC |
Hearing Documents
Decision
Make a representation
The application can be inspected under the application plans and documents heading below.
You will be able to comment on this application until 3 October 2024
Please base your comments on planning matters.
Please avoid the use of inflammatory, discriminatory or abusive comments
All representations made in connection with the development proposal will be made publicly available on the website shortly after the end of the representation period. The name of the individual author or organisation will be published however addresses, signatures and contact details will not be published. We advise you not to include any other personal information about yourself or others.
OurCustomerPrivacy Noticesets out how we handle personal data in accordance with the law.
Send your comments via email to section62a@planninginspectorate.gov.uk
or write to
Section 62A Applications Team,
The Planning Inspectorate,
3rd Floor, Temple Quay House,
2 The Square, Temple Quay,
Bristol,
BS1 6PN
Sending comments by email will enable us to deal with them more quickly and is preferred.
Please include the application reference number S62A/2024/0058 and site address.
This application will be determined by an Inspector appointed by the Secretary of State. Shortly after the close of the representation period the Planning Inspectorate will consider whether a hearing is necessary. In the event that a hearing is scheduled, and you would wish to speak at the hearing, you must make this request at the time you submit your written representations.
Where the application is to be considered at a hearing, notice of the date, time and venue for the hearing along with the name of the person holding the hearing, will be published on this website at least two weeks before the date of the hearing.