Guidance: Section 62A Planning Application: S62A/22/0006 Berden Hall Farm, Ginns Road, Berden (Redetermination)

Planning Inspectorate

July 18
14:23 2024

Following a High Court challenge to our decision on this application dated 9 May 2023 the Court has ordered that the application be re-determined. This does not necessarily mean we will reach a different overall decision.

Type of application:

Full Planning Application

Applicant name:

Berden Solar Limited

Site address:

Berden Hall Farm, Ginns Road, Berden

Description of proposed development:

Development of a ground mounted solar farm with a generation capacity of up to 49.99MW, together with associated infrastructure and landscaping

Case Officer:

Major Casework Team

Procedure: Hearing

Key dates:

Date
Date by when representations must be made 8 January 2024
Hearing date and venue 10.00am on Tuesday 26 March 2024 at Council Chamber, Uttlesford District Council, London Road, Saffron Walden, CB11 4ER Hearing Notification (PDF, 80.5 KB, 1 page)
Date by when comments on Site Selection Report must be made: 11 April 2024
Date by when any final comments by the applicant must be made: 18 April 2024
Date by when signed Unilateral Undertaking must be submitted: 18 April 2024
Decision date 18 July 2024

Hearing Documents

Related Articles

Comments

  1. We don't have any comments for this article yet. Why not join in and start a discussion.

Write a Comment

Your name:
Your email:
Comments:

Post my comment

Recent Comments

Follow Us on Twitter

Share This


Enjoyed this? Why not share it with others if you've found it useful by using one of the tools below: