At approximately 08:22 hrs on 28 March 2015, the 08:25 hrs Acton Yard to Merehead Quarry freight service, reporting number 7C29 (running approximately one hour early) passed signal T1729 on the Up Westbury line at Reading West Junction by about 20 metres.

In a separate incident at approximately 06:12 hrs on 3 November 2015, the 06:22 hrs Acton Yard to Merehead Quarry freight service, reporting number 7C29 (running approximately one hour early) passed signal T1627 at Ruscombe (near Twyford) at danger by about 60 metres.

Both trains were operated by DB Schenker (DBS). In both cases, the driver applied the trains brakes when the train was close to the respective signal, and before the Train Protection and Warning System at the signal intervened, but not in time to prevent the train passing the signal at danger.

For both incidents, the initial evidence suggests that driver fatigue may have been a factor. Other similarities between the two incidents were that they involved the same train service and occurred approximately seven miles apart. In both cases the drivers had booked on duty around midnight, worked a train from Westbury to Acton, and then after taking a layover at Acton, departed with their return working to Westbury approximately one hour early.

Our investigation of the two incidents will include examination of:

  • the sequence of events
  • the arrangements for reporting, monitoring and managing fatigue
  • any other recent incidents involving freight trains where fatigue may have been a factor (including an accident involving a signal being passed at danger and subsequently derailing on trap points at Santon New Junction (near Scunthorpe) on 7 August 2015)
  • the response to recommendations made by the RAIB following previous relevant incidents involving fatigue, with particular reference to the RAIBs investigation into the runaway at Shap on 17 August 2010 (RAIB report 15/2011)
  • any relevant underlying management factors.

Our investigation is independent of any investigation by the railway industry or by the industrys regulator, the Office of Rail and Road.

We will publish our findings, including any recommendations to improve safety, at the conclusion of our investigation. This report will be available on our website.

You can subscribe to automated emails notifying you when we publish our reports.

Related Articles

Comments

  1. We don't have any comments for this article yet. Why not join in and start a discussion.

Write a Comment

Your name:
Your email:
Comments:

Post my comment

Recent Comments

Follow Us on Twitter

Share This


Enjoyed this? Why not share it with others if you've found it useful by using one of the tools below: