The NDA Mission Progress Report (MPR) demonstrates the progress being made across the NDA group since 2005, and how much work there is left to do over the next 120-plus years.
Progress is described as the work being done in four important areas to reduce the hazards at our sites. Those areas are set out in our Strategy:
- spent fuel
- nuclear materials
- integrated waste management
- site decommissioning and remediation.
There are many different ways in which the Report describes the progress weve made. Some of those include how many buildings weve demolished, how much fuel weve reprocessed and how much waste weve treated and stored. Weve used the same metrics for land, buildings and nuclear inventory, providing a clearer and more consistent picture for people to understand.
The following milestones were all completed in the financial year 2022 to 2023 thanks to reprocessing coming to an end:
- All Magnox reprocessing completed
- All exotic fuel reprocessing completed
- All plutonium produced
- All uranium produced
This means we have now completed 8 of our 47 strategic outcomes.