The Mission Progress Report 2023 to 2024 outlines the progress of the NDAs mission to decommission the UKs early nuclear sites safely, securely, and cost-effectively. The report aligns with the our strategy and focuses on our four driving themes: Spent Fuels, Nuclear Materials, Integrated Waste Management, and Site Decommissioning and Remediation. ?

Key highlights include:

  • Spent Fuels: All Magnox reactors are defueled, and reprocessing has ended. ? Remaining spent fuel is in interim storage. ?
  • Nuclear Materials: Plutonium is consolidated at Sellafield, and uranium consolidation is ongoing. ?
  • Integrated Waste Management: Significant progress in waste retrieval and treatment, with a focus on legacy facilities. ?
  • Site Decommissioning and Remediation: Ongoing decommissioning and land remediation to release sites for future use. ?

The report emphasises the importance of continuous monitoring, adapting to new technologies, and ensuring the safe management of radioactive waste. The NDAs mission is crucial for supporting the UKs energy security and achieving carbon net zero goals. ?

Updates to this page

Published 18 November 2024

Sign up for emails or print this page

Related Articles

Scroll Back To Top 📄More Articles

Comments

Scroll Back To Top Write Comment
  1. We don't have any comments for this article yet. Why not join in and start a discussion.

Write a Comment

Scroll Back To Top
Your name:
Your email:
Comments:

Post my comment

News Calendar

Recent Comments

Follow Us on Twitter

Share This


Enjoyed this? Why not share it with others if you've found it useful by using one of the tools below: