GovWire

Report 09/2022: Collision between road-rail vehicles near Ramsden Bellhouse

Rail Accident Investigation Branch

September 1
11:02 2022

R092022_220901_Ramsden_Bellhouse

Summary

On 2 May 2021, just before 07:00 hrs, two road-rail vehicles (RRVs) collided while travelling on the same track towards Wickford station from a location of work near Ramsden Bellhouse, Essex. The leading vehicle, a mobile elevating work platform (MEWP), was stationary at the time of the collision and was hit from behind at around 7.5 mph (12 km/h) by a road-rail machine, configured as a crane. The MEWP operator suffered life-changing injuries due to the collision.

Around 10 seconds before the collision, the MEWP operator had stopped to stow away a tool which was loose in the personnel basket of his machine. Around the same time, the operator of the crane became dazzled by the rising sun ahead. The crane operator turned to look out of the side window to relieve his eyes but did not apply the brakes of the crane when he did so, resulting in the collision with the MEWP.

Before the collision, the crane operator had allowed the gap between the crane and the MEWP to reduce so that, when the MEWP stopped, it was only about 30 metres. Network Rail standards require operators to maintain a minimum separation distance of 100 metres when travelling in convoy with other vehicles. The shortened separation distance in this case reduced the time that the crane operator had to observe and react to the obstruction ahead.

Fatigue was a possible factor in this accident, as the crane operator had not taken advantage of the opportunity to rest before the nightshift at a hotel provided by his employers. He had also not declared his actual travel time when providing his journey details at the site access control point.

A possible underlying factor was the lack of clarity in the role of machine controllers during travelling movements. This may have contributed to a lack of warning of the impending collision from the crane controller, who was riding in the cab with the crane operator.

A similar collision occurred at Wellingborough on 15 August 2019. The industrys investigation into that accident found that the machine operators involved had been regularly ignoring the need to maintain an adequate separation between vehicles. Although action was taken to modify behaviours, site inspection procedures were not revised to assure compliance and RAIB found that the plan for the work being undertaken on 1 to 2 May 2021 did not explicitly cover the need for suitable distances to be maintained. Not applying learning from this previous accident is also a possible underlying factor.

Recommendations

RAIB has made three recommendations. Two of these are addressed to Network Rail and include the need to clarify the role of a machine controller when they are travelling with their vehicle, as well as the need to continue the development of obstacle detection for road-rail vehicles. A third recommendation is made to SPL Powerlines UK and Readypower Rail Services relating to the application of learning from previous accidents and incidents.

RAIB has also identified four learning points. These alert operators to the need for bringing vehicles to a stand when forward vision is lost, and the importance of judging and observing the correct safe distance between moving vehicles. It is also important that staff are fit and appropriately prepared when reporting for duty and comply with all road-rail vehicle operating instructions.

Published 1 September 2022

Related Articles

Scroll Back To Top 📄More Articles

Comments

Scroll Back To Top Write Comment
  1. We don't have any comments for this article yet. Why not join in and start a discussion.

Write a Comment

Scroll Back To Top
Your name:
Your email:
Comments:

Post my comment

News Calendar

Recent Comments

Follow Us on Twitter

Share This


Enjoyed this? Why not share it with others if you've found it useful by using one of the tools below: